HB399 takes effect in219d 12h 41m— Cloverleaf is racing this deadline.See the 5 demands →
LOWNDES COUNTY · ALABAMA · A COMMUNITY COALITIONLOWNDES DESERVES A BETTER DEAL
45#45strong.net
← All harms
§02 · The Harm — Power & Your Bills

Your power bill goes up. Theirs doesn't.

Across the country, residential ratepayers are paying for hyperscale data centers' power demand. Alabama Power's promise that we won't is a promise — not a tariff filing.

USGS aerial of the Hope Hull industrial corridor, Montgomery County, Alabama, with surrounding transmission infrastructure visible.
FIG. P·1Hope Hull, Montgomery County. A hyperscale data center is, in grid terms, a small city's worth of electrical demand on a single private meter, with substations and high-voltage feeders sized to match. Source: USGS National Map, public domain
+$11.24/mo
approved 2026 residential rate increase, Dominion VA — driven by data-center load
+833%
PJM capacity-market clearing-price jump for 2025–2026
the power consumption of all of Lowndes County, combined — described to residents for Project Red Clay

What Cloverleaf and the EDC say.

Lowndes County Economic Development Board chair Thomas Ellis has cited assurances from Alabama Power and PowerSouth that “current rate-payers will have no impact from future data centers.”P1 Cloverleaf has echoed the framing: the data center is its own customer, on its own meter, and existing households will not subsidize it.

What that leaves out.

The promise is unbacked by a tariff filing. There is no rate schedule, no rate class, and no public utility commission ruling that binds Alabama Power to its own assurance. Independent reporting from PJM (the wholesale electricity market that includes Virginia, Ohio, and parts of the Southeast) tells a different story: as hyperscale data-center demand has surged, capacity-market clearing prices for the 2025–2026 delivery year jumped 833%. Those costs land on residential ratepayers' bills.P2

Virginia's State Corporation Commission, November 2025: the typical Dominion residential customer will pay an additional $11.24 per month in 2026, driven principally by data-center load. Ohio residential customers are paying ~$16/month more from the same PJM dynamic. Georgia introduced SB 34 to bar utilities from passing data-center costs to other customers.— Inside Climate News, Virginia Mercury, EESI, CNBC reporting November 2025 – April 2026.P3
High-voltage electrical transmission lines and pylons against the sky.
FIG. P·2High-voltage transmission and distribution infrastructure of the kind that has to be built — and paid for — to deliver hyperscale data center load. Across PJM, capacity-market clearing prices for the 2025–2026 delivery year jumped 833%. Those costs land on residential ratepayers. Source: Wikimedia Commons, CC BY-SA 3.0

The “rate class” argument is the proof.

Across multiple states, regulators are now moving to create a separate rate class for hyperscale data centers — precisely because, under the existing tariffs, residential and small-business customers were absorbing the cost of new generation, transmission, and capacity. Virginia just did this. Ohio is doing this. Georgia passed legislation. The fact that the regulatory action was needed is the evidence that the original promise didn't hold.

Alabama has not yet acted. There is no Alabama Public Service Commission rate-class filing for hyperscale loads. There is no binding agreement that prevents Project Red Clay's eventual operator — whoever it turns out to be — from putting upward pressure on residential bills.

Alabama Power has already started building generation for unproven demand.

On December 3, 2025, the Alabama Public Service Commission approved Alabama Power's purchase of the Lindsay Hill natural gas generating station in Billingsley. The justification: a forecasted surge in electricity demand from data centers in Alabama over the next few years.P6

The Southern Environmental Law Center, citing a December 2025 Greenlink report, argues the load forecast supporting that purchase is approximately 0.2% likely to materialize as projected. In other words, Alabama Power has already committed capital — capital that will eventually flow to ratepayers through the rate base — for demand that has roughly a one-in-five-hundred chance of showing up.P7P8

This is exactly how the cost lands on residential customers, even when the developer "promises" it won't. The pattern is documented; the regulatory protections that have arrested it elsewhere have not yet been adopted in Alabama.

Ohio's regulatory protections caused data-center demand requests to crash.

After Ohio adopted ratemaking provisions similar to Virginia's new large-load rate class — provisions that require data-center customers to pay for what they actually demand, not pass it through to residential ratepayers — the volume of data-center demand requests in Ohio fell from roughly 30 gigawatts to 13 gigawatts.P9

That is the most concrete evidence available that ratepayer-protection regulation does not "kill" data-center investment — it filters out the speculative pipeline. The projects that survive are the ones a region actually needs and that pay their own way. Alabama can adopt the same protections at the Public Service Commission and produce the same effect.

Virginia: $11.24/month additional residential charge, approved Nov 2025.P10 Ohio: $16/month residential cost from PJM capacity adjustments.P11 Ohio's protections cut demand requests from 30 GW to 13 GW. Virginia created a new GS-5 large-load rate class effective January 2027.P12— Multiple sources, Nov 2025 – May 2026.

The scale.

A single hyperscale data center can draw 100+ megawatts of electric power.P4 The site Cloverleaf has described to residents would consume three times the power of all of Lowndes County, combined.P5 Serving that load requires new generation, new transmission lines, and grid upgrades. Someone pays for those. The question on the table for the Commission is: who?

Estimated electrical load, megawatts
All of Lowndes County, current peak~50 MWProject Red Clay (per Judge Johnson, 3× county)~150 MW
FIG. — Order-of-magnitude comparison. Project Red Clay sized from Judge Adrian Johnson's quote that the proposed facility would use three times as much power as everything in Lowndes County currently.

The question for the Commission.

What you do next matters more than what you read here.

Send the demands. Call your commissioner. Show up.

Every name on the petition is a name on the public record at the next commission meeting. Every phone call lands on a staffer's notepad. Every demand letter forces an on-the-record answer to a question Cloverleaf has not been able to answer.

Lowndes County deserves a better deal.

Tenant disclosure · Water transparency · Ratepayer protection · Education-tax carve-out · Tenant-binding agreement

Read the demandsSend the demands →